Tuesday, 15 September 2015

Wall prep finished

Week Four.
 
I have now done as much as I can on preparing the wall. It still needs some attention using either jet washer or sand blaster to remove the old grey limewash but Iapart from concentrating on the odd brick, I think another method has to be better.
 
View of the gardens from the access platform

Friday, 11 September 2015

More work on wall - no builders on site

Week Four

No builders on site this week as they were allowing time for the concrete footings to set.  Weather wise, it has been fantastic. I have nearly finished removing the mortar from the bricks and did a bit more cleaning of them,  but I am going to leave the worst bits for the pressure washer or sand blaster as it is a painfully slow process.
 
View of brick wall from the garden
Brick wall after quite a lot of work. Starting to look better but a long way to go!
The concrete footings being left to set
View of shed area from bathroom
Close up of wall ready for re-pointing

Sunday, 6 September 2015

Working on the wall

Week Three.
 
I have been working on the wall this weekend.  Parts of the paint covering come away quite easily,  but some of the grey areas are a rock solid limewash.  I have to literally chip away with a paint scraper trying my best not to damage the surface of the brick underneath. It is slow progress,  but I can really see a difference in the two images.
 
Before...
After...

Saturday, 5 September 2015

Digging complete!

Week Three.
 
The guys have worked so hard this week - they reckon around 50 tonnes of soil have been removed in total!
 
Trenches were dug for drainage pipes and they were then back filled with shingle.  The foundation trenches were then dug and filled with concrete.
 
Pipes ready to go into the ground to feed rainwater from roof into soakaway
Gravel lines mark the location of pipes buried in the ground which will take rainwater from the roof
Freshly poured concrete foundations and now covered over soakaway (gravel area bottom centre)

Wednesday, 2 September 2015

Footings and soakaway preparations

Week Three.
 
Work was completed on digging out all the soil to the necessary depth today. Now work is starting in digging down to create a soakaway - I hadn't realised that this involved digging an area down another five feet in order to put plastic honeycomb cages in. The lovely dark soil was finished and they were down to a chalk and clay mix - not great.
 
The black plastic crates are for the soakaway which will be a further five feet down into the ground
The hole starting for the soakaway - note the change in soil type - much harder to dig!

Tuesday, 1 September 2015

Week Three - still digging...

Week Three.
 
After a rainy Bank Holiday Monday it was back to work today and the digging out continues. The weather was perfect so now only a small amount of soil remains to be taken away. Lots of old bottles were found in a rubbish dump area - most with a Salisbury manufacturer marked on the glass - it will be interesting to find a date for when that company was in business.
 
I used some brick and patio acid after work had finished for the day on my brick wall to see if it would remove some of the coal dust and limewash, but although it helped remove the limewash it took a lot of effort and didn't touch the coal dust staining.  It was Jewsons brand so I will check the strength of acid and may have to use a stronger one.
 
View from the bathroom - you can see the amount of grey limewash on the brick wall - it is going to take a lot of work!

Friday, 28 August 2015

Week Two - progress after a rainy start.

Week Two.
 
Work didn't begin this week until Thursday due to heavy rain. We had the hole in the ground and I was worried that it would fill up with water but it drained away well and didn't turn the ground into a quagmire which I was really pleased about.
 
Work continued digging out the shed area and the same for next door.  We have been discussing the material to be used for the retaining wall and have decided to use railway sleepers which will be protected by a damp proof membrane and a layer of gravel. We are going to go for new green oak sleepers and use a preservative rather than the old and oily reclaimed version as the kids may want to sit on the steps and I don't want them getting covered in oil and tar!
 
View of the gardens.  Note the scaffolding tower and access over the wall into the Churchyard
View from the back bedroom