Week Sixteen.
Dan worked all weekend making the most of a good spell of dry weather and managed to get the majority of the box frame up. Work has continued today with the box frame being completed and some of the six king posts being put in position. Standing down on the scalpings today directly in front of the buildings gave me the first sense of how big they are actually going to feel. Up until now, the floor space felt small and there was no way of imagining what the front of the building was going to look like.
|
Huge progress after a lot of hard work plus weekend working! |
|
The middle vertical post marking the position of the mezzanine/storage section (to the left) and the main utility part (on the right). |
|
The two front vertical posts marking where our doors will be. |
|
Brick pier and oak frame meeting |
|
View from the garden |